Thursday, May 5, 2016

Clay lime roof plaster

We shall see how this works.  I need to putsomething over this brick roof to keep water from seeming into the brick kiln and to collect the water for making more bricks.

This is clay soil sand and lime plaster, then second day and third day to press it with trowels to make it more impervious and harder.  Somewhat like Tadelakt.  


The question is what will happen when the roof gets very hot from the burning.

This is the inside



this is the outside




This is after day two


smoothening with a scrapper.

Thursday, April 14, 2016

brcik kiln vault and chimney


It took awhile to finish the vault over the kiln.  Part of the reason was we closed down.  We got an big order and so have started burning again.

Dickson and Elia both came and we closed the vault and made the chimney.  from the base it is about 6m, and there is about 3m from the opening in the top of the vault.  It is massive.

So last week on Tuesday it was fired up.  the first few hours the chimney was not pulling.  By noon it was pulling out.  The second day it was pulling more.  There are lots of leaks in the vault , mostly at vault ends between the end walls and the doors.




I will experiment some with the chimney height, and the opening being bigger and smaller.  I also think the cover should be removed during firing.


What it does do is get the steam, smoke, gases, and hot air higher up and less of an issue for neighbors.





Note the buttresses.  Even then i am a bit nervous.  this is a big vault.  5.5m wide and 8.5 meters long.



the wood roof needs to go as it catches on fire now.  the vault gets so hot.  And then a new system to waterproof and catch the water.


Sunday, April 3, 2016

Maize storeage shed

We are almost done with this  building s for storing maize cereal after harvest until the price is right. Later it could be a car garage and outside storeage and maybe where chicks are kept.





The process.

Foundation was all stone.  Dry laid except last 30 cm, then a lime sand mortar.  On top of the stone was a 20 cm reinforced concrete beam, which  might  be overkill.


I overlapped the rammed sections.  Since then I have learned to not overlap and go straight up with no bond.  It is going to crack anyway 1/2 the time.
Note the  brick column around the garage door.  This made it easier I thought rather than cutting a board each time .  Also this way the ears of the door are set in the bricks instead of rammed earth.


The electrical boxes posed a problem as the ramming causes them to deform.  So you ram soil in the boxes before installing them.


The plastic water pipe for conduit does deform , because it is round?  my friend Roland says to take them all up instead.




These came out nice .  although there is a slight issue you see in the middle.  Need the guys to be more aware of how it will bond on the edge, sweep the top of the previous one, wet it, make sure the cornors are packed good.




On the back wall is a small window where we used boards as end pieces for around the window.  Then a brace to keep it in place. Had some issues with poor quality here.

Note the damp proof course and the notched end pieces.  The bricks below was formwork for the beam.

I used neighborhood boys who are unskilled and untrained.  They made a few mistakes but are catching on.  The need to check and recheck plumb.



Where do i get the soil?  From the trenches of the foundations and from an area I want to build another house with basement.  I learned to keep it covered so to control moisture in the mix.  It is best drier as opposed to wetter.



Reaching lintel height and I start cantilevering bricks to make eaves and form work for a ring beam for the vault to spring off of.  This was done by skilled mason.

 Reclaimed door frame, with arch over it.

 You can see the brick work for ring beam.

The wall came out reasonably well.

Inside showing the wall, arches and the ringbeam brick formwork


 At the door way i put in wedges so the corners don't break.  I should of done at corners also.
 Vault time.
 Note:
-tie rods as the room is 8 meters long.  Don't weld bolts on the end of rebar, but rather have them threaded.
-strings to keep shape.


 always pleasant to look at masonry ceilings, or?

Real scaffolding


Timbrel?  Not really.  As this is a very flat arched vault the individual vaults can "pop".  The layer above serves to stop the popping.  It also makes the roof more rigid and stronger, however increases the weight and hence thrust on the walls.  Okay it is timbrel.

On top of the second layer a clay sand plaster to make it smooth to put a plastic vapor barrier.

On the short ends we needed a overhang of the walls, and we tried to cantilever the vaults but it didn't work.  kept popping off.  this wall will get some driving rain but the rammed earth should be able to withstand and dry off between rains.



Some aluminum tubes lined with tinfoil for extra light.

Soome trials with aluminum tubes with bottles on the outside in the roof.  this is with flash and there was dust or insects flying around.

 Same picture withoug flash.


the bottle light in the roof during day time.




the reclaimed metal door need some reclaimed wood.  Old Pallets and particle board from crates.

What i need to avoid.  there is some splashing on the ground from the eaves here splashing back on the wall.  dissappears in the day from a night rain.
 On the long walls the eaves overhang about 22 cm.  I dont see a problem.  The above problem will be remedied by some gravel.

What remains is the rammed earth floor and the roof.  Both are challenges.


Floor.

We dug out all the top soil about 50cm.  then i filled with what we call mouram.  It is volcanic gravel, very corse.  this is vapor barrier.  It will not wick water.  then a layer of  broken bricks for a flat  platform for rammed earth.  So it doesnt dissappear into the gravel.  This is the first try with rammed earth floor and this is the first layer.  10cm of clay/sand and 8% lime.



You should let the first course dry before the smooth slurry but i wanted to try a test ares.  this is 1:1 clay soil and sand.  it takes forever to dry.
 Here i tried smoothing the rammed earth, it is possible to get smooth.

The roof i was originally was thinking living sod roof.  I am worried about the weight and roots going through weak plastic.  Then i did a test of rammed earth painted with lime wash.  I realise that will not work as it gets wet and dries repeatedly.  I think clay is out.  Then i thought of just covering the plastic on the roof with mouram light gravel.  Simply to protect the plastic from sun.  I might try that.  I also might try some sod along the bottom.

As i am playing with clay, next building i might have roofing tiles.